Pennsylvania Lien & Bond Claim Masterclass: Everything They Don’t Tell You (But Should!)

Learn Pennsylvania lien deadlines, notice of intent and Notice of Furnishing rules, bond claims, and CASPA payment rights in this masterclass.

ARIELA WAGNER

by

Ariela C. Wagner

|

WORKER SMILING

Attorney Reviewed

Last updated:

November 17th, 2026

Published:

November 17, 2026

10 mins

Read

Getting paid is the number one challenge on Pennsylvania construction projects, and the further down the payment chain you are, the harder it gets. Pennsylvania gives contractors, subcontractors, and suppliers powerful tools, including mechanics liens, payment bonds, and CASPA, but each comes with strict notices and deadlines. In this webinar, construction attorney Chad Michaelson explains how to use them to protect your right to payment.

In this webinar, presented by SunRay Construction Solutions and Pennsylvania construction attorney Chad I. Michaelson of Meyer, Unkovic & Scott LLP, contractors, subcontractors, and suppliers learn the strategies that protect their right to get paid in Pennsylvania. This guide covers mechanics lien deadlines, the Pennsylvania construction notices directory, payment bond claims, contract terms to negotiate, and your rights under the Contractor and Subcontractor Payment Act (CASPA).

Key Takeaways

  • Every claimant must file a Pennsylvania mechanics lien within 6 months after finishing its work. Subcontractors must also serve a formal notice of intent at least 30 days before filing, which leaves them about 5 months in practice.
  • After filing, the lien must be served within 30 days, and a lawsuit to enforce it must be filed within 2 years.
  • If your project is listed in the Pennsylvania construction notices directory, you need to file a Notice of Furnishing before you start your work to protect your lien rights.
  • Public projects cannot be liened in Pennsylvania. Your protection there is the payment bond, so get a copy of the bond before you start work.
  • On private projects, CASPA sets default payment deadlines and 1% per month interest on late payments, but your contract terms can change those defaults.

Watch the Full Webinar

Watch the full presentation by Chad Michaelson of Meyer, Unkovic & Scott LLP below, or browse more sessions in our Past Webinars library.

Why Payment Protection Matters in Pennsylvania

Payment is the number one challenge on construction projects. Michaelson noted that about 90% of the cases he handles involve payment in some way, whether it is simple late payment, a dispute over whether payment was earned, or a fight over a change order.

The further down the payment chain you are, the harder it gets. A general contractor only has to watch one link: the owner. A subcontractor or supplier has to make sure its customer pays, and also that nothing is going wrong between its customer and the parties above it. When money takes 45, 60, or 90 days to flow down to you, that becomes a cash flow problem for your business.

Pennsylvania gives you several tools to protect your right to payment: mechanics liens, payment bonds, your contract, and CASPA. Each one has requirements and deadlines, and you need to know them before payment problems start.

How Pennsylvania Mechanics Liens Work

A mechanics lien exists because the law recognizes that you put labor and materials into a building while the owner keeps all of its value. If the owner does not pay, it is not fair for the owner to keep the benefit of your work.

The lien is a claim against the property, not against the owner personally. Its power comes from leverage: an unresolved lien can interfere with the owner's project financing, so the owner has a strong reason to get it resolved.

In Pennsylvania, lien rights extend to parties within two tiers of the owner. That includes the general contractor, subcontractors, and sub-subcontractors and suppliers.

Filing a lien does not put money in your pocket by itself. To actually get paid, you have to file a lawsuit to enforce, or foreclose, the lien.

Pennsylvania Mechanics Lien Deadlines

The table below summarizes the key Pennsylvania lien deadlines.

StepWhoDeadline
Notice of Furnishing (if the project is listed in the construction notices directory)SubcontractorsBefore you start your work
Notice of intent to file a lienSubcontractors and suppliers30 days before filing the lien (within 5 months of your last work)
File the lienGeneral contractors, subcontractors, and suppliersWithin 6 months of your last work
Serve the filed lienAll lien claimantsWithin 30 days after filing
File a lawsuit to enforce the lienAll lien claimantsWithin 2 years after filing the lien

Subcontractors Really Have Five Months

A general contractor has 6 months to file a lien. Subcontractors and suppliers have the same six-month deadline, but they must also give a notice of intent 30 days before filing. For all intents and purposes, that means subcontractors have 5 months to serve the notice of intent and 6 months to file the lien.

Michaelson cautioned against waiting until the last day. A lot goes into preparing a lien, and waiting until the end of month five leaves no room for error before the six-month deadline.

Track Your Last Day of Work Carefully

The six months run from the last day you performed your actual scope of work. According to Michaelson, punch list and warranty work generally do not extend the deadline. Substantial completion can be a useful marker, but trades that finish early, such as site work, need to track their own last date and calendar the deadlines from it.

Identify the Property and Owner Early

Your lien must correctly identify the property it covers. If the property is misidentified, you could lose your lien rights. Confirm who owns the property and how it is identified in the county records at the start of the job, not on the last day before filing.

Serve the Lien Within 30 Days

Once you file a lien, you only have 30 days to serve it. If it is not served within 30 days, it is defective. Michaelson recommended getting the lien to the sheriff the same day it is filed, because some sheriffs are busy and slow. If the owner cannot be found and served, the lien can be posted on the property.

CTA - Don't let a missed deadline cost you your payment rights. Track notice, lien, and bond claim deadlines automatically. - Sign Up Now

Check the Pennsylvania Construction Notices Directory

Pennsylvania created a registry, the Pennsylvania construction notices directory, where the owner of a project over a certain value can register the project. You can find it by searching online for "Pennsylvania construction notices directory" and then search for your project.

If your project is listed in the directory, you need to file a Notice of Furnishing before you start your work. The Notice of Furnishing alerts the owner that you are a subcontractor on the project. If you do not file it on a project that is listed in the directory, you lose your lien rights.

According to Michaelson, if you file the notice late, you can have lien rights from the time you filed it, but not for amounts you were unpaid before that.

When Lien Rights Are Not Available

Public Projects

Public projects cannot be liened in Pennsylvania. On public work, your protection is the payment bond, covered below.

Private Projects With a Payment Bond and No-Lien Agreement

On a private project, a subcontractor can lose the right to file a lien in one situation: the general contractor has posted a payment bond guaranteeing payment to subcontractors, and a no-lien agreement has been filed with the court in the county where the project is located. In that case you would make a bond claim instead. Because the agreement must be filed in the public record, you should know about it before you start, so review it before you sign your contract.

Lien Waivers on Commercial Projects

On a nonresidential, commercial project in Pennsylvania, nobody can ask you to waive your lien rights. You cannot waive your lien rights until you are paid, unless there is a payment bond posted, you have notice of it, and it has been recorded with the county. That is the only situation where your lien rights go away.

Payment Bond Claims in Pennsylvania

A payment bond is a guarantee from a surety, essentially an insurance company, that you will be paid if the contractor defaults. When you make a bond claim, the contractor will often tell its surety that you are not owed the money, for example because the owner has not paid or because of back charges. To the extent there is no legitimate dispute and you can prove what you are owed, the surety will pay your claim.

  • Public projects: you will have a bond. Payment bonds are required by state law on public projects.
  • Private projects: sometimes there is a bond and sometimes there is not. It depends on whether the owner wants to spend the money.
  • Deadlines: you need a copy of the bond to know its notice requirements and deadlines. There is often a tight limit to file on the bond. It might be one year, or it might be less if the bond says so.

Michaelson's advice: find out whether the project is bonded and ask for a copy of the bond when you sign your contract. Once payment stops, contractors are often slow to provide it, and you can miss a deadline simply because you never saw the bond.

Liens and bonds are separate tools. When both are available, you should use both.

Contract Terms That Protect Your Payment

Liens and bonds only cover the value of the labor and materials you supply. They generally do not cover attorney fees, lost productivity, or other increased costs. Your contract is where you protect those. Michaelson recommended reviewing these provisions before you sign:

  • Avoid pay-if-paid clauses. A pay-if-paid clause means you only get paid if the owner pays your customer. A pay-when-paid clause is fairer: you agree to wait a set period, such as 7 or 14 days after your customer is paid, but you can still pursue payment if the owner never pays.
  • Add a right to suspend work. Try to include the right to stop work if you are not paid on time. The statutory suspension process under CASPA takes much longer.
  • Include attorney fees. Even a mutual fee provision is better than none. Without it, you may spend money on a lawyer just to collect what you are already owed.
  • Watch for waivers. Some subcontracts try to waive your right to a change order when you are delayed or interfered with. Even if such a clause might not be enforceable, you do not want it in your contract.
  • Protect your retainage. Make sure the contract gives you the right to get retainage back, so it is not held for months after you finish just because the owner has not released it.

Your Rights Under CASPA

The Contractor and Subcontractor Payment Act (CASPA) applies to private projects in Pennsylvania. There is a similar prompt payment law for public projects.

  • Payment timing: the owner has to pay the contractor within around 20 days, and the contractor has to pay subcontractors within 14 days after the owner pays the contractor.
  • Interest: if an owner or general contractor misses a payment deadline, interest accrues at 1% per month.
  • Pay application problems: if your pay app is wrong or missing supporting documents, they only have 10 days to tell you that you have to fix it. If they do not, they waive that right.
  • Withholding for disputed work: if they are going to withhold part of a payment for defective work, a lien, or something else, they have to tell you within 14 days, and they can only withhold the disputed part. They have to pay the undisputed amount. Michaelson stressed that keeping all of the money because of a small dispute is illegal under CASPA.
  • Attorney fees: if the owner withholds payment in bad faith and you have to sue, the court could award attorney fees. You are still better off putting an attorney fee provision in your contract.
  • Right to suspend work: CASPA has a provision allowing you to suspend work, but it takes probably 60 or more days of nonpayment before you can actually use it.

Your Contract Can Change CASPA's Defaults

According to Michaelson, what the contract says matters, and the contract trumps CASPA. CASPA just sets defaults. If your contract has a longer payment deadline, the contract governs. And if you agree in your contract to no interest, you get no interest. The 1% is the default if the contract does not say otherwise. That is why it pays to read and negotiate your contract.

CTA - Still not paid? SunRay helps construction businesses protect payment rights and get paid faster. Prepare and serve notices, liens, and bond claims with one streamlined platform. - File Now

Practical Tips to Protect Your Right to Get Paid

  • Read your contract. Know the payment terms, retainage, lien provisions, and how to protect your right to a change order.
  • Make your pay applications perfect. Submit them on time with every required document, such as certified payrolls. An incomplete pay app gives the owner a reason to delay payment.
  • Put claims and issues in writing. Follow the contract's notice provisions exactly, whether that means certified mail, overnight delivery, or email, and keep proof of delivery.
  • Do not waive more than you are paid for. When signing a waiver, carve out any amounts still in dispute.
  • Calendar every deadline. Once a deadline passes, your leverage is gone.
  • Pay your own subs and suppliers. Pass undisputed amounts down the chain and follow CASPA yourself.
  • Be the squeaky wheel. Raise your lien and bond rights as soon as payment slows down. The threat of a lien is often as effective as the lien itself.

FAQs

Can a Pennsylvania mechanics lien be amended?

Only in limited ways. According to Michaelson, you generally cannot increase the amount of a filed lien. If more money becomes due, you may need to file a new lien within the six-month deadline. Amendments are usually limited to minor details, so talk with SunRay or counsel before changing a lien.

What if I cannot serve the notice of intent on the owner?

The notice of intent goes to the owner and the contractor, and it does not have to be served by the sheriff. It is typically sent by mail with proof of delivery. If one party is ignoring you, Michaelson suggested working with the other to get the notice delivered.

What if the sheriff cannot serve my filed lien on the owner?

Get the lien to the sheriff the day you file it and keep on them. If two weeks pass and they have not served it, think about other options. Posting the property is a good one. Remember that you only have 30 days after filing to serve the lien.

Does punch list or warranty work extend my lien deadline?

Generally no. The six-month deadline runs from the last day you performed your actual scope of work.

Can a contractor make me waive my lien rights in advance on a commercial project?

No. On a nonresidential, commercial project, nobody can ask you to waive your lien rights until you are paid. The only exception is when a payment bond has been posted, you have notice of it, and it has been recorded with the county.

Do these rules apply outside Pennsylvania?

No. Everything in this webinar is specific to Pennsylvania. Every state has its own lien laws, deadlines, and required documents. Visit the SunRay Pennsylvania resources page and the resources for the other states where you work.

Protect Your Pennsylvania Payment Rights With SunRay

Pennsylvania lien and bond deadlines are tight, and one missed step can cost you your leverage. SunRay prepares and serves notices of intent, Notices of Furnishing, mechanics liens, and payment bond claims, and tracks your deadlines so you do not miss one. For more on what happens after filing, read what happens after you record your lien in Pennsylvania.

Create your SunRay account to protect your next Pennsylvania project, or register for an upcoming webinar.

FAQs: Fundamentals of Lien Laws

No items found.

About Author

ARIELA WAGNER

Ariela C. Wagner

Ariela is the president and founder of SunRay Construction Solutions. She has over 20 years of construction industry experience. Read More>

WORKER SMILING

Protect your Pennsylvania lien and bond claim rights before deadlines pass. Let SunRay track and file for you.

Get Started

Contact Us Today

Want to get paid faster? Contact us by filling out the below form!

Thank you! Let's get you paid!
Oops! Something went wrong while submitting the form.
Subscribe to Newsletter