Read

California’s prompt payment laws give contractors, subcontractors, and design professionals a powerful way to get paid. When payment is withheld without a good-faith dispute, several statutes impose a penalty of 2% per month (24% per year) and let the winning party recover attorney fees and costs. In this webinar, construction attorney William L. Porter explains each statute, the deadlines that apply, and how to use these laws as leverage without going to court.

In this webinar, presented by SunRay Construction Solutions and California construction attorney William L. Porter, Founder & President of Porter Law Group, Inc., contractors, subcontractors, and design professionals learn how California’s prompt payment laws work and how to use them to get paid. Several of these statutes impose a penalty of 2% per month (24% per year) on payments that are wrongfully withheld, and they let the winning party recover attorney fees and costs. This guide covers each statute Porter discussed, the payment deadlines, the good-faith dispute limit, and how to use these laws as leverage before you ever need a lawyer.

Key Takeaways

  • Several California statutes impose a 2% monthly penalty (24% per year) on wrongfully withheld construction payments, and the prevailing party recovers attorney fees and costs.
  • Subcontractors at every tier must be paid within 7 days after the party above them receives payment for their work.
  • On private projects, owners must pay progress payments within 30 days of a payment demand and release retention within 45 days after completion.
  • Only amounts disputed in good faith are excluded, and the paying party can withhold no more than 150% of the disputed amount.
  • These rights apply by law even if your contract is silent. Put your payment demand in writing and ask the other side to respond in writing if they disagree.

Watch the Full Webinar

Watch the full presentation by William L. Porter of Porter Law Group, Inc. below, or find it in our Past Webinars library.

What Are California’s Prompt Payment Laws?

California’s prompt payment laws are statutes that set deadlines for paying contractors, subcontractors, and design professionals on construction projects. When a party misses the deadline without a good-faith dispute, it owes a statutory penalty on the unpaid amount. On many private and public projects, that penalty is 2% per month, and the prevailing party in a collection action can recover reasonable attorney fees and costs.

The rules work in two directions:

  • Owner to prime contractor: if the owner does not pay the prime (direct) contractor on time, the prime can claim the penalty and attorney fees.
  • Down the payment chain: if the party above you has been paid for your work and does not pass that payment on to you without a good excuse, you can claim the same remedies. This applies to subcontractors and to subcontractors of subcontractors.

These protections are part of the law. You do not need to write them into your contract for them to apply. According to Porter, the real value of these statutes is not in a lawsuit. It is in using them to show the other side that delaying your payment will cost them far more than paying you.

California Prompt Payment Deadlines at a Glance

The table below summarizes the statutes covered in the webinar. Each one applies to a specific type of project, payment, and relationship, so start by finding the row that matches your situation.

PaymentWho Pays WhomDeadlineLate-Payment RemedyStatute
Private progress paymentOwner to direct contractor30 days after a payment demand2% per month (in place of interest) + attorney feesCivil Code § 8800
Private retentionOwner to direct contractor45 days after completion2% per month (in place of interest) + attorney feesCivil Code §§ 8812, 8818
Private retentionDirect contractor to subcontractor10 days after receiving the retention2% per month (in place of interest) + attorney feesCivil Code §§ 8814, 8818
Progress payments, all tiers (private and public)Prime contractor or subcontractor to subcontractor7 days after receiving payment (21 days on public utility contracts)2% per month + attorney feesBus. & Prof. Code § 7108.5; Pub. Contract Code § 10262.5; Civil Code § 8802
Public progress paymentState agency to contractor30 days after an undisputed payment requestInterest at 10% per yearPub. Contract Code § 10261.5
Public progress paymentCalifornia State University to contractor39 days after the payment requestInterest at the legal rate (10% per year)Pub. Contract Code § 10853
Public progress paymentLocal agency to contractor30 days after an undisputed, properly submitted requestInterest at the legal rate (10% per year)Pub. Contract Code § 20104.50
Public retentionPublic entity to original contractor60 days after completion2% per month (in place of interest) + attorney feesPub. Contract Code § 7107
Public retentionOriginal contractor to subcontractor7 days after receiving the retention2% per month (in place of interest) + attorney feesPub. Contract Code § 7107
Design services (public works)Public agency to prime design professional30 days (progress) or 45 days (final retention) after a written demand1.5% per month (in place of interest) + attorney feesCivil Code § 3320
Design services (public works)Prime design professional to subconsultant15 days after receiving payment1.5% per month (in place of interest) + attorney feesCivil Code § 3321
CTA - Don't let a missed deadline cost you your payment rights. Track California notice, lien, and bond claim deadlines automatically. - Sign Up Now

Private Works: Progress Payments From Owner to Direct Contractor

Under California Civil Code Section 8800, an owner on a private project must pay the direct contractor any undisputed progress payment within 30 days after the contractor demands payment under the contract (in practice, after you submit your billing), unless the owner and contractor agree otherwise in writing.

If the owner misses that deadline, the owner owes a penalty of 2% per month on the amount wrongfully withheld, in place of any other interest. That matters because most contract interest rates are lower. A typical contract might allow 12% per year, or 1.5% per month (18% per year). The statutory penalty replaces that rate with 24% per year. The prevailing party can also recover attorney fees and costs.

Private Works: Retention Payments

California’s private works retention rules are in Civil Code Sections 8810 through 8822. Two deadlines matter most:

  • Owner to direct contractor: under Civil Code Section 8812, an owner that withholds retention must pay it within 45 days after completion of the work of improvement.
  • Direct contractor to subcontractor: under Civil Code Section 8814, once the direct contractor receives all or part of a retention payment, it must pay each subcontractor its share within 10 days.

If retention is wrongfully withheld, the penalty is again 2% per month in place of interest, and the prevailing party recovers attorney fees and costs. The same good-faith dispute limit applies: an amount disputed in good faith, plus 50%, is excluded from the penalty. If you are a subcontractor on a private project, track when the owner releases retention to the direct contractor so you know when your 10 days begin.

Payments to Subcontractors at Every Tier

Porter called this one of his favorites because it is so broad. Business and Professions Code Section 7108.5 and Public Contract Code Section 10262.5 cover both private and public projects and apply at all tiers: a prime contractor paying a subcontractor, and a subcontractor paying its own subcontractor.

The rule: unless otherwise agreed in writing, a prime contractor or subcontractor must pay a subcontractor within 7 days after receiving each progress payment for that subcontractor’s work. If it does not, it owes a penalty of 2% per month, and the prevailing party in a collection action recovers attorney fees and costs. A violation of Section 7108.5 is also cause for disciplinary action by the Contractors State License Board.

Why the Penalty Can Exceed 24% a Year

Porter explained that under these two statutes the 2% monthly penalty is in addition to the interest stated in your contract, not in place of it. If your contract charges 1.5% per month and the statutory penalty adds 2% per month, the combined rate is 3.5% per month, or 42% per year. He recommends that every contract include an interest rate, and says 1.5% per month is a rate California judges generally accept.

That number makes a persuasive argument. As Porter put it, you can tell the other side you will gladly take your 42% and let them pay whenever they like, because no investment guarantees that kind of return. How a court or arbitrator applies the two rates together will depend on your contract and the facts of your case.

Public Utility Projects

When the direct contract is with a public utility, Civil Code Section 8802 gives the direct contractor 21 days (not 7) after receiving a progress payment from the utility to pay its subcontractors, unless they agree otherwise in writing.

Public Works: Progress Payments From Government Owners

On public works projects, the deadline for the owner’s progress payment to the contractor depends on which public entity owns the project. These statutes protect the contractor directly below the public owner, not subcontractors. The remedy is interest at 10% per year rather than 2% per month, so the leverage is smaller, but a guaranteed 10% is still a strong argument.

State Agencies

Under Public Contract Code Section 10261.5, a state agency that fails to make a progress payment within 30 days after receiving an undisputed, properly submitted payment request owes the contractor interest at 10% per year. If the agency improperly rejects a payment request, the interest can start earlier.

California State University

Under Public Contract Code Section 10853, California State University has 39 days after receiving a contractor’s payment request to pay before interest at the legal rate (10% per year) begins. An improper rejection of the request can start interest sooner, and withholding is limited to amounts disputed in good faith.

Local Agencies

Under Public Contract Code Section 20104.50, a local agency such as a city, county, or district must pay a progress payment within 30 days after receiving an undisputed, properly submitted payment request, or pay interest at the legal rate (10% per year).

Public Works: Retention Payments

Public Contract Code Section 7107 governs retention on public works. The public entity must release retention to the original contractor within 60 days after completion of the work. The original contractor must then pay each subcontractor its share of the retention within 7 days after receiving it.

Retention that is not paid on time is subject to a charge of 2% per month in place of interest, and the prevailing party recovers attorney fees and costs. The same limit applies to amounts disputed in good faith. Porter noted he has used this statute, like the others in the webinar, to great effect for clients.

Design Professionals: Architects, Engineers, and Surveyors

Two Civil Code sections protect licensed architects, engineers, and land surveyors on public works projects:

  • Public agency to prime design professional: under Civil Code Section 3320, the agency must pay progress payments within 30 days and the final retention within 45 days after receiving a written demand for payment.
  • Prime design professional to subconsultant: under Civil Code Section 3321, the prime must pay each subconsultant design professional within 15 days after receiving a progress or final retention payment.

For both, the penalty is 1.5% per month (18% per year) in place of interest, plus attorney fees and costs to the prevailing party. Porter stressed that a demand does not have to say “I hereby demand.” A bill is a demand for payment. Because the statute calls for a written demand, send your invoice in writing and keep proof of the date it was received.

How the Good-Faith Dispute Limit Works

Prompt payment penalties do not apply to amounts that are disputed in good faith. However, the paying party cannot use a small dispute to hold back an entire payment. Under most of these statutes, it may withhold no more than 150% of the disputed amount. Everything above that remains subject to the penalty.

Porter’s example:

  • You are owed $100,000.
  • There is a good-faith dispute over a $2,000 change order.
  • The other side may withhold 150% of the disputed amount, or $3,000, without a penalty.
  • The remaining $97,000 is subject to the penalty. At 2% per month, that is $1,940 per month.

Whether a dispute is truly in good faith is ultimately for a judge or arbitrator to decide. Disputes that appear only after you demand payment, with no earlier complaint about your work, are harder for the other side to defend. Our guide to California statutory releases explains how to preserve disputed amounts when you sign waivers.

How to Use Prompt Payment Laws to Get Paid Without a Lawsuit

Porter’s main advice was to avoid attorneys, including him, whenever you can. Litigation is slow and expensive. The better approach is to use these statutes as tools that make paying you the easiest choice for the other side. If they refuse, they face paying their own attorney, your attorney, the amount they owe, and the penalty on top.

An effective written communication should:

  • State the facts. Identify the work, the amount owed, the date you billed, and, if you know it, the date the party above you was paid.
  • Name the statute and the remedy. State the penalty rate that applies and that you will be entitled to attorney fees and costs.
  • Acknowledge any genuine dispute. For example: “You owe $100,000, although we have a dispute regarding a $2,000 change order.”
  • Put the burden on them to respond. Close with a line such as: “If you disagree with anything stated above, please respond to me in writing within seven days so that I understand the nature of your disagreement.” The deadline can be shorter, such as 48 hours.

If the other side does not respond, that silence works against them. A judge or arbitrator may conclude that because they did not dispute your letter when asked, they did not disagree. In one example Porter shared, the owner wrote back confirming the amount owed and citing only financial problems, which established the facts without any attorney involvement. As Porter put it, “he who has the most paperwork usually wins.”

CTA - Still not paid? SunRay prepares and serves California mechanics liens, stop payment notices, and payment bond claims. - File Now

Combine Prompt Payment Claims With Liens, Stop Payment Notices, and Bond Claims

Prompt payment penalties are one tool. California also gives you mechanics liens, stop payment notices, and payment bond claims. Porter recommends using every tool available and telling the other side so in your letter: you are owed the statutory penalty, and you are also prepared to record a lien, serve a stop payment notice, or make a claim on the payment bond.

You can pursue all three at the same time. Each has its own deadline, so work from the shortest one. Mechanics lien recording deadlines can be as short as 30 days after a notice of completion is recorded, and a lawsuit to foreclose a lien must be filed within 90 days after the lien is recorded. Stop payment notice and bond claim enforcement deadlines are different and can be longer. To learn what happens next, read what to do after you record a California mechanics lien.

FAQs

Do prompt payment penalties have to be written into my contract?

No. The penalties and attorney fee provisions come from the statutes, so they apply even if your contract says nothing about interest. Some payment deadlines, such as those in Civil Code Section 8800 and Business and Professions Code Section 7108.5, apply “unless otherwise agreed in writing,” so check whether your contract changes them. Porter also recommends including a contract interest rate, such as 1.5% per month.

Is 24% a year interest or a penalty?

Under most of these statutes, the 2% monthly charge is a statutory penalty that replaces ordinary interest. Over a full year it equals 24%. Under Business and Professions Code Section 7108.5 and Public Contract Code Section 10262.5, Porter explained that the 2% penalty is added on top of your contract interest rate.

Can a contractor delay paying subs because the bank is holding the owner’s funds?

Porter does not believe so. None of these statutes has an exception that lets a bank acting as an intermediary extend the payment deadline. If a bank hold could excuse late payment, the statutes would not work.

Should I send a mechanics lien, stop payment notice, and bond claim at the same time?

Yes, that is fine. Each remedy has different deadlines, so use the shortest one to time all three. After that, track the lawsuit deadline for each.

What counts as a payment demand?

A demand does not need special wording. Submitting your bill or payment application is a demand for payment. Keep a written record of when it was sent and received.

Do these rules apply outside California?

No. Everything in this webinar is specific to California. Every state has its own prompt payment rules, deadlines, and documents. Visit the SunRay California resources page and the resources for the other states where you work.

Get Paid on California Projects With SunRay

Prompt payment penalties work best when you have also protected your lien, stop payment notice, and bond rights. SunRay prepares and serves California preliminary notices, mechanics liens, stop payment notices, and payment bond claims, and tracks the deadlines so you do not miss one. When a matter needs an attorney, SunRay can provide the completed documents to send to your lawyer.

Create your SunRay account to start protecting your payment rights on your next California project, or register for an upcoming webinar.

FAQs: Fundamentals of Lien Laws

No items found.

About Author

ARIELA WAGNER

Ariela C. Wagner

Ariela is the president and founder of SunRay Construction Solutions. She has over 20 years of construction industry experience. Read More>

WORKER SMILING

Not getting paid on a California project? Protect your lien, stop payment notice, and bond claim rights with SunRay.

Get Started

Contact Us Today

Want to get paid faster? Contact us by filling out the below form!

Thank you! Let's get you paid!
Oops! Something went wrong while submitting the form.
Subscribe to Newsletter